Construction
Requirements Letter
(Name
and Address of Awardee’s
Authorized Representative)
| Subject: |
Project
No. __________ |
| |
(Awardee
Name) |
| |
(City,
State) |
| |
“Information
for Grantee” |
Dear
Mr. _________:
This
is to inform you that our office, the
“Health Care and Other Facilities”
(HCOF) program office is responsible for
certifying that your grant funded project
will be designed, bid, constructed, and
ultimately completed in accordance with
all applicable federal requirements. To
that end, our involvement will require
the receipt of proper documentation and
concomitant certification from you at
various phases of the project.
We
have received a copy of the “Notice
of Grant Award” issued. Therefore,
we outline below the procedures which
shall be followed for the oversight of
the various phases of your project.
-
If you have not yet done so, it is expected
that you will engage the services of
an architect/engineer (A/E) to develop
the pertinent construction documents
as well as to supervise the construction
phase of the project. Accordingly, your
A/E will submit to the HCOF program
office a pre-certification statement
attesting to his suitable involvement
in this project (see enclosed “Architect/Engineer
Pre-Certification Statement”).
This statement should be submitted
to the HCOF program office within 30
days from the date of this letter. If
this deadline is not feasible, it is
imperative that you contact us to work
out an extension in time.
-
The project must be designed in accordance
with the mandatory requirements imposed
on federally-assisted construction projects
as well as all applicable program standards,
state codes, and local codes and ordinances.
Accordingly, your A/E will certify (before
construction bidding and contract award)
that the final working drawings and
final technical specifications were
so developed (see enclosed “Architect/Engineer
Certification of Final Design”).
It is expected that the design
documents will be completed by the estimated
completion date so stated in the pre-certification
statement, and that the certification
of final design statement will be submitted
to the HCOF program office within 30
days from that date.
-
You must certify that the various bonding
and insurance requirements for federally-assisted
construction projects will be met (see
enclosed, “Statement of Assurance
of Grantee’s and Contractor’s
Bonding and Insurance Coverage”).
-
It is your responsibility to make every
effort to award the construction contract(s)
under a process where maximum competition
is achieved in order to obtain the most
reasonable price. Therefore, competitive
bidding by formal advertisement must
be used except when construction management
procedures are employed.
Accordingly, you will submit to us your
bid tabulations, certified by your A/E,
and your formal recommendation of award.
The recommendation should also include
a statement of determination that the
selected contractor is not on the U.S.
General Services Administration Lists
of Parties Excluded from Federal Procurement
or Non-Procurement Programs (debarred
list). If you award the contract to
any qualified bidder other than the
lowest bidder, provide proper documentation
for your decision. Subsequently, a copy
of your award letter(s) to the successful
contractor(s) will also be submitted
to the HCOF program office. The
bid tabulations, certification, award
recommendation, “debarred list”
statement, award letter, and bonding
and insurance statement (see item 3)
must be submitted within 30 days from
the scheduled contract award date.
-
During the construction phase, submit
a quarterly construction report informing
us of the progress of the project including
problems/issues that were observed or
need to be addressed. This report should
include the percentage of project completion
to date, the start date for the project,
projected completion date, the drawdown
percentage of the awarded funds, and
a description of the status of the project.
The status description should include
any major problems/delays, change orders,
changes of scope, or any other issues
related to the status of the project.
The quarterly report must be
submitted on a timely basis, no later
than 30 days from the end of the report
period. IF THE REPORT IS NOT SUBMITTED,
IT MAY HAVE AN EFFECT ON THE AWARD DRAW
DOWNS.
-
Submit written notification to the HCOF
program office when the project is completed.
The letter will include statements assuring
that the project has been completed
in accordance with the previously certified
contract documents and that the project
is free of mechanics’ liens. (Also
see related item 7 below,)
-
You must sign, date and submit to the
HCOF program office a statement in which
you certify: 1) that the project has
been constructed in conformance with
the applicable federal statutes and
regulations, 2) the final project costs
and their respective allowable and non-allowable
components (submit a final SF 424C “Budget
Page”) and 3) the Substantial
Completion Date, 4) a copy of the certificate
of occupancy issued by the Authority
Having Jurisdiction, and 5) photographs
of the front and rear of the project
and each of the major rooms in the project,
with a brief description. The
notification of project completion letter
(see item 6), certification statement
with attached SF 424C, certificate of
occupancy, and descriptive photographs
must be submitted within 30 days of
project completion.
We
look forward to working with you toward
a successful project. The HCOF program
office is committed to processing your
project in an orderly and prompt manner.
Cooperation between the HCOF program office
and you, the grantee, is crucial to ensure
the continued disbursement of your grant
funds without interruption. Mr. ___________
of my staff has been designated as your
DFCR Project Manager. He can be reached
at (301)-443-____ or (301)-443-0619 (fax)
or __________@hrsa.gov (preferred method).
The mailing address for the HCOF program
office is 10-105 Parklawn Building, 5600
Fishers Lane, Rockville, MD 20857.
| Sincerely, |
| |
Paul
T. Murphy, MBA
Chief, Facilities Monitoring Branch
|
| enclosures: |
Architect/Engineer
Pre-Certification Statement
Architect/Engineer Certification to
Final Design
Applicant’s Assurance –
Bonding and Insurance Coverage |
|