Organization Name: Family Medical Center (FMC)
Project Type: Construction of a New Facility
Project Name: FMC New Facility
Total CPF/CDS Funding Request = $490,000
Total Project Cost = $8,302,100
Our proposed Community Project Funding/Congressionally Directed Spending (CPF/CDS) project will construct a new, 3-story building on an existing site.
The building will provide:
- examination rooms
- Waiting area,
- Records rooms
- Patient services
- Provider offices
- Special purpose room
- Restrooms
- Healthcare support function areas
- Communications
- Mechanical spaces.
The building will comply with all accessibility requirements of the Americans with Disabilities Act and local building codes.
Additionally, we’ll install an FMC sign at the entrance of the facility, and purchase moveable medical and office equipment.
The building will result in a larger and better organized facility, well-suited to deliver patient services.
The FMC project cost is $8,302,100. With this application, we request $490,000 to support the construction and equipment cost. For the balance of $7,812,100 we’ll use a loan backed by HRSA’s loan guarantee program.
If you don’t approve the loan guarantee program application, we’ll use $4,500,000 of program income. In addition, we’ll use venture capital financing from local investors for the $3,312,100, in which we have already received letters of support.
We anticipate the project will begin within 30 days of award. We’ll complete and occupy it by August 2025.
Allowable Costs—CPF/CDS |
Unallowable Costs |
|
---|---|---|
Line 1— Administrative and legal expenses |
$23,600 for a portion of FMC’s staff/project manager (work related to the construction project) $39,500 for environmental analysis and costs associated with evaluation of the environmental effects of proposed activities and producing an Environmental Statement to the local authorities Total administrative cost: $63,100 |
|
Line 2—Land, structures, right- of-way, appraisals, etc. |
FMC owns the land. We don’t need more land for this project. |
|
Line 3—Relocation expenses and payments |
Although this project requires temporary relocation, we don’t anticipate any costs. |
|
Line 4— Architectural and engineering fees |
Covers:
Total architectural and engineering fees: $739,000 |
|
Line 5—Other architectural and engineering fees |
Don’t anticipate any |
|
Line 6—Project inspection fees |
Includes:
Total: $23,437 |
|
Line 7—Site work |
Includes:
Total: $375,000 |
|
Line 8—Demolition and removal |
None |
|
Line 9— Alteration/ Renovation (Construction) |
$6,067,563 is the total construction cost to build the new building on the existing site. The total square footage is 17,358 square feet on three levels. The master format divisions costs are: $540,012 total general requirements
$4,963,266 total facility construction
$345,852 total facility services
$169,891 total process equipment
$48,542 total other project costs
$6,067,563 Grand total construction cost |
$10,000 is an allowance for a wall mural in the waiting room. |
Line 10— Equipment |
$96,000
$38,750 for office equipment:
$569,250 of clinical equipment. Total = $704,000 |
|
Line 11— Miscellaneous |
Don’t anticipate any |
|
Line 12—SUBTOTAL (Allowable and Unallowable Costs) |
$7,972,100 total allowable costs |
$10,000 total unallowable costs |
Line 13— Contingencies |
$320,000, which is less than 5% of the sum of Lines, 7, 8, and 9 |
|
Line 14— SUBTOTAL |
$8,292,100 total allowable costs |
$10,000 total unallowable costs |
Line 15—Project (program) income |
Not Applicable |
|
Line 16—TOTAL PROJECT COSTS (Allowable and Unallowable) |
$8,302,100 (Sum of allowable and unallowable costs from Line 14 above) |
|
Line 17— GRANT funding requested (Note: round to the nearest whole dollar amount) |
$2,000,000 |
SEE APPENDIX B: Allowable and Unallowable Costs in the guidance documents.